- AIA Contract
- Liability and Workers comp insurance
- AIA Schedule of values
- Finalized job schedule, showing complete phasing of the job
- Weekly schedule updates
- Two week “look-ahead” schedules
- Weekly safety meetings run by job superintendent
- Daily meetings with subcontractor foremen by job superintendent
- Weekly job meetings on site with owner, architect, PM Construction Project
- Manager and Superintendent, and appropriate subcontractors
- Weekly meeting minutes sent out to all involved parties
- Submittal Log
- Change Order Log
- RFI (requests for information) Log
- Monthly requisitions with draft copy for review before submission
- Management of all plan changes